Ernest Henry underground mine 

In December 2009, Xstrata Copper announced the approval of a US$542 million investment to extend the life of our Ernest Henry mine in north Queensland, Australia to at least 2025 through the transformation of open pit mining operations to a major underground mine together with the construction of an associated magnetite extraction plant. The images below capture the progress of construction works at the site.

November 2012
Construction of the main headframe continues while the shaft sink progresses at approximately 1.5 metres per day. Over 200 metres of development has been reached of the 1,000 metre shaft
November 2012
Construction of the main headframe continues while the shaft sink progresses at approximately 1.5 metres per day. Over 200 metres of development has been reached of the 1,000 metre shaft
May 2012
Peter Bosgra, winder driver from Byrnecut. Shaft sinking commenced in May 2012 for the hoisting shaft that will enable production to double, in time, from our underground mine
May 2012
Peter Bosgra, winder driver from Byrnecut. Shaft sinking commenced in May 2012 for the hoisting shaft that will enable production to double, in time, from our underground mine
March 2012
The shed that houses the sinking winders is complete with construction commencing for the main headframe that will transport ore from underground to the surface
March 2012
The shed that houses the sinking winders is complete with construction commencing for the main headframe that will transport ore from underground to the surface
November 2011
Final touches are made to the 28-metre tall temporary headframe with installation of all six sinking winders underway
November 2011
Final touches are made to the 28-metre tall temporary headframe with installation of all six sinking winders underway
August 2011
Preparations were underway for the shaft sink to commence at the end of 2011
August 2011
Preparations were underway for the shaft sink to commence at the end of 2011
August 2011
Sky-shaft construction nears completion and winder shed construction commences
August 2011
Sky-shaft construction nears completion and winder shed construction commences
June 2011
First shipload of magnetite concentrate leaving the port of Townsville, in June 2011 bound for the Asian market
June 2011
First shipload of magnetite concentrate leaving the port of Townsville, in June 2011 bound for the Asian market
April 2011
First shipment of magnetite concentrate
Loaded onto a train destined for the Port of Townsville, in north Queensland, where it will be exported to Asia
April 2011
First shipment of magnetite concentrate Loaded onto a train destined for the Port of Townsville, in north Queensland, where it will be exported to Asia
January 2011
Underground Project 
The underground shaft collar and headframe foundations Complete
January 2011
Underground Project The underground shaft collar and headframe foundations Complete
January 2011
Underground Project  
First of two fans to be installed underground for improved ventilation 
Installation 90% complete
January 2011
Underground Project First of two fans to be installed underground for improved ventilation Installation 90% complete
January 2011
Magnetite plant 
Regrind plant area Civil works 
90% complete
January 2011
Magnetite plant Regrind plant area Civil works 90% complete
January 2011
Underground Project Portal 
An excavator loads material from underground into a haul truck
January 2011
Underground Project Portal An excavator loads material from underground into a haul truck
January 2011
Extension project
Magnetite first concentrate produced
January 2011
Extension project Magnetite first concentrate produced
January 2011
Magnetite filter plant 
complete
January 2011
Magnetite filter plant complete
January 2011
Magnetite plant 
First production of magnetite concentrate
January 2011
Magnetite plant First production of magnetite concentrate
October 2010
Underground Project Cooling towers associated with the refrigeration system 
Complete
October 2010
Underground Project Cooling towers associated with the refrigeration system Complete
July 2011
Construction is underway for the sky-shaft used to complete the main shaft sink
July 2011
Construction is underway for the sky-shaft used to complete the main shaft sink